What this computed plan shows
Numbers, not decorative lines, define the 5kW 48V Workshop Solar Wiring Diagram PDF (5S2P). The 5S2P field connects 10 panels for 5 kW of nameplate power, 220 operating volts and 23.6 short-circuit amps. That combination gives a workshop builder a concrete starting case that can be changed in the linked customizer.
Controller sizing follows two separate limits in this workshop configuration. Power conversion calls for 131 A or more at the battery side, and cold-array allowance raises the PV check from 260 V nameplate Voc to 325 V. The selected MPPT envelope is 150 A and 400 V.
PV current is evaluated at 36.8 A for the 41 ft array run, which selects 8 AWG copper plus a 40 A OCPD. Charging current is 104.2 A across 6 ft, moving the recommendation to 3/0 AWG copper with 150 A protection. Each percentage in the table is a round-trip voltage-drop calculation.
For storage, the computed arrangement is 4S1P, assembled from 4 × 100 Ah LiFePO₄ batteries. Series connection establishes the 48 V nominal level, while parallel strings bring the bank to 100 Ah. The displayed 5,120 Wh is nominal capacity rather than a promise of daily usable energy.
The inverter contributes 83.3 A of continuous DC input at the engine’s efficiency assumption. Over a 2 ft one-way cable path, 1 AWG copper and a 110 A protective device keep calculated drop at 0.11%. Its 7,200 W surge label is recorded for equipment comparison, but the schedule must still be checked against the chosen inverter manual.
This page stays inside the verified engine boundary: every component and conductor currently returns a within verdict. A different panel label, longer run, hotter ambient or changed battery count can alter that result, so follow the customize link rather than scaling the picture by intuition. Local rules, equipment listings and inspection requirements take precedence over this planning aid.
For later comparison, keep the 5 kW array, 4S1P bank and the 41/6/2 ft one-way routes together when requesting equipment quotes or an inspection review.
Wire, protection and battery schedules
Wire schedule
| Segment | Design current | One-way run | Computed conductor | Voltage drop | Sizing basis |
|---|---|---|---|---|---|
| array → controller | 36.8 A | 41 ft | 8 AWG copper | 1.07% | 156% of array Isc (NEC 690.8) |
| controller → battery | 104.2 A | 6 ft | 3/0 AWG copper | 0.2% | controller output at 125% continuous-load ampacity |
| battery → inverter | 83.3 A | 2 ft | 1 AWG copper | 0.11% | inverter continuous DC input at 90% efficiency and 125% ampacity |
Overcurrent protection
| Protected segment | Required ampacity | OCPD | Conductor ampacity | Verdict |
|---|---|---|---|---|
| array → controller | 36.8 A | 40 A | 40 A | within |
| controller → battery | 130.2 A | 150 A | 165 A | within |
| battery → inverter | 104.2 A | 110 A | 110 A | within |
Battery arrangement
| Arrangement | Chemistry | Units | Unit capacity | Bank capacity | Nominal energy | Nominal voltage |
|---|---|---|---|---|---|---|
| 4S1P | LiFePO₄ | 4 | 100 Ah | 100 Ah | 5,120 Wh | 48 V |
Static routed parts list
Parts are computed from this passing configuration. A route appears only when the verified catalogue record proves every displayed numeric rating; all uncertain matches stay local for verification. Routed links may earn Off Grid Authority a commission at no extra cost to you.
Pre-install review steps
- Confirm the array and controller window: Verify that the 5S2P string plan produces 260 V open circuit and that the equipment is rated above the 325 V cold-design value.
- Lay out the protected DC runs: Measure the one-way paths before ordering cable, then compare them with the computed 41 ft, 6 ft and 2 ft runs shown here.
- Build complete battery strings: Arrange all 4 battery units as 4S1P; do not leave a partial series string in a 48 V bank.
- Commission against equipment instructions: Check polarity, terminal torque, DC interrupt ratings, conductor temperature ratings, ambient correction and local inspection requirements before energizing the 3,600 W inverter.
Customize or compare